Realignment of a 185m length, 3m x 3m tail race tunnel.
Sector 
Power and electricity
Feature 
Project rectified collapse of existing tunnel section.
“Overcoming the difficulties of a remote location.”

This project involved the realignment and new construction of a 3m x 3m x185m of tailrace tunnel due to a previous section of the existing tunnel collapsing.


The tunneling method was drill and blast and temporary support was provided by a variety of rock bolts, mesh, steel sets and timber support. Permanent in-situ concrete secondary lining was also installed following installation of ground support.

Contact us

Send an email or give us a call if you would like to make a comment, require more information or need some advice.

 
1 Start 2 Complete

Abergeldie Harker
Floor 1, Suite 2 Annex, 27 Gillies Avenue, Auckland 1023
PO Box 9888, Newmarket, Auckland 1149, New Zealand

T   +64 9 295 2570
E   info@abergeldieharker.co.nz